Project

saturation diving campaign at Okume field and Ceiba FPSO

Client

Trident Energy

Rana Scope of Work

  • WI Flowline Tie-in at Bravo platform (via cold tap clamp) on an existing Flowline going to Alpha platform and WI Flowline Tie-in at Delta platform on a rigid spool
  • 10” WI Riser Replacement at Okume Delta platform
  • 6” Spool Installation at Okume Delta platform
  • 24” Subsea Hoses Change-Out at Ceiba FPSO

 

Project Data

Location

Equatorial Guinea

Dates

14/03/2022 to 25/04/2022

Diving techniques

saturation diving

Duration

43 days

Resources

Vessel

  • MSV Bourbon Evolution 802

 

 

 

Diving Systems

  • Sat Diving System AF05
  • Air Diving System

Personnel

  • Diving team: 42
  • ROV team: 6