Project

Diving support services for FSO Alba Marina riser replacement – Rospo Mare Field - Italy

Client

Edison

Rana Scope of Work

  • n.2 x 8” flowlines PLEM-Mid buoy removal and replacement with new flowlines
  • n.1 x 8” flowline Mid buoy-FSO removal and replacement

 

Project Data

Location

Adriatic Sea - Rospo Mare Field, offshore Italy

Dates

2/11/2017 to 28/11/2017

Diving techniques

  • Saturation diving
  • Surface-supplied air diving

Duration

26 days

Vessels

MPSV Mamta

Diving Systems

Rana Saturation Diving System AF1

Air Diving System

Personnel

Diving team: 34

Main equipment

  • Hydraulic tensioning tools
  • Subsea welding/cutting
  • Lifting equipment
  • Installation tools
  • Acoustic leak detection system